Transportation

Polk County US-64 Rockslide Update for March 12

Friday, March 12, 2010 | 12:36 pm
Midnight at the rockslide
Midnight at the rockslide
Work on put-in ramp
Work on put-in ramp
24 Hour Schedule Continues
 
CHATTANOOGA, Tenn. – Crews continued working a 24 hour schedule with hand and mechanical scaling, drilling, and blasting proceeding on the eastern side of the main slide area and along the river bank during daylight hours and rock bolting operations taking place on the western slope during night time hours.  This schedule is expected to continue through the weekend and into next week as weather permits.  Night time rock bolting operations are expected to shift to a 24 hour, 7 day a week schedule as soon as the slope blasting and scaling operations are completed.
 

U.S. 25/70 in Cocke County to Close for Bridge Inspection

Friday, March 12, 2010 | 11:15 am
TDOT to Detour Traffic During Inspection
 
Knoxville, Tenn. – Motorists using U.S. 25/70 (State Route 9) will need to take an alternate route Wednesday, March 17 when TDOT bridge inspectors close the bridge over the French Broad River in Newport to perform a routine bridge inspection.
 
U.S. 25/70 (State Route 9 or East Broadway) in Newport will be closed from 9:00 a.m. until 3:00 p.m. on March 17. Motorists will be detoured onto U.S. 321 and State Route 340.
 

All lanes temporarily opened on The Spur

Tuesday, March 09, 2010 | 02:47 pm
Mold used to make concrete panels for rock facade
Mold used to make concrete panels for rock facade
Concrete panels to be used to make rock facade
Concrete panels to be used to make rock facade
Knoxville, Tenn. –  Behind the scenes work has allowed the Tennessee Department of Transportation to temporarily open all lanes of U.S. 441 (The Spur) in Sevier County.
 
Emergency contractor Charles Blalock and Sons, Inc. is currently working offsite utilizing molds to pour concrete panels that will form a stained rock façade which will cover the recently constructed retaining wall. The retaining wall was built during phase one of the project to stabilize the rock slope above the roadway.
 
TDOT estimates crews will begin to install the rock façade during the week of March 15. At that time one southbound lane will close to allow crews to safely work on phase two of the rockslide repairs.

Recovery Act Funds to Provide More Intercity Bus Service Options to Tennesseans

Tuesday, March 09, 2010 | 02:43 pm
NASHVILLE – The Tennessee Department of Transportation will use federal American Recovery and Reinvestment Act funds to provide rural residents with better access to daily public transit. Vice President Joe Biden announced federal approval of TDOT’s plan to use $3.1 million in Recovery Act funds to expand direct intercity bus routes on Friday, March 5. The funds will be used by existing intercity bus carriers to purchase 23 buses, security equipment, support vehicles, computers, intelligent transportation system software, for ADA enhancements to vehicles and preventive maintenance. TDOT announced the first intercity bus routes in the state in March 2009. The program provides fixed route public transportation services between rural areas and the state’s urban centers.
 

Polk County US-64 Rockslide Update for March 8

Monday, March 08, 2010 | 03:14 pm
Workers continue to remove debris from the boat ramp located at the foot of TVA Ocoee 2 Dam.
Workers continue to remove debris from the boat ramp located at the foot of TVA Ocoee 2 Dam.
Crews Move to 24-Hour Work Schedule
 
CHATTANOOGA, Tenn. – Work continues to progress on the stabilization and clearing of the rockslide along U.S. 64 at Mile Marker 17 in Polk County with around the clock work set to begin Tuesday. Construction crews with TDOT’s emergency contractor on the site, Charles Blalock & Sons, set off a series of blasts this weekend along the rock slope located east of the rockslide site. Today, crews are extending the crane pad for the 275-ton crawler crane further east to provide better access to the eastern slope for debris and rock removal work. On the west side of the slope, workers continue drilling and installing rock bolts and will begin working a 6:00 p.m. – 6:00 a.m. rock bolting schedule on Tuesday. The contractor will perform scaling, blasting and clearing work during daylight hours and rock bolting during the night.
 

Polk County US-64 Rockslide Update for March 5

Friday, March 05, 2010 | 05:24 pm
A large crane hoists a platform, which holds a worker operating a mini-excavator, up the side of the mountain to remove loose rock and debris.
A large crane hoists a platform, which holds a worker operating a mini-excavator, up the side of the mountain to remove loose rock and debris.
CHATTANOOGA, Tenn. – Work continues to progress on the stabilization and clearing of the rockslide along US64 at Mile Marker 17 in Polk County. Construction crews with TDOT’s emergency contractor on the site, Charles Blalock & Sons, today drilled along the eastern side of the slope in preparation for blasting scheduled for Saturday.  Rock bolting crews are working along the western slope throughout the weekend.
 

Polk County US-64 Rockslide Update For March 3

Wednesday, March 03, 2010 | 04:33 pm
Debris Removal
Debris Removal
Drilling the Slope
Drilling the Slope
More Drilling, Blasting, Hauling and Rock Bolting
 
CHATTANOOGA, Tenn.  - Over the weekend, crews broke up the rock on the roadway surface from last week’s eastern slope blast using the large ram-hoe, and the material was hauled off of the site. On Monday crews continued drilling and grouting rock bolts on the eastern slope. 
 
Yesterday crews continued working on both the eastern and western slope with machine scaling and rock bolting operations, although all hand work was suspended because of snow and ice on the slope surface. Drilling operations resumed today on the eastern slope in preparation for blasting later in the week.
 

TDOT Reopens U.S. 441 Southbound in Sevier County

Monday, March 01, 2010 | 03:51 pm
A large 100 ft. wide and 20 ft. high retaining wall structure is now in place to secure the unstable mountainside.
A large 100 ft. wide and 20 ft. high retaining wall structure is now in place to secure the unstable mountainside.
Knoxville, Tenn. – The Tennessee Department of Transportation re-opened one lane of US 441 (The Spur) southbound in Sevier County shortly before 3:30 p.m. this afternoon, nearly two weeks ahead of schedule. TDOT was forced to close the southbound lanes of the roadway after a rockslide threatened the stability of the mountainside on January 25. 
 
“We understand this has been an inconvenience to many people traveling to and from Gatlinburg and are pleased to see the contractor reopening the roadway ahead of schedule,” said TDOT Commissioner Gerald Nicely.
 
Since the rockslide occurred, motorists traveling southbound into Gatlinburg have been utilizing one of the northbound lanes. With the southbound lane now reopened, TDOT expects to remove the detour and reopen both northbound lanes to northbound traffic by Tuesday, weather permitting.
 

Polk County US-64 Rockslide Update For February 26

Friday, February 26, 2010 | 02:22 pm
Workers prepare to lift the drill into place by crane
Workers prepare to lift the drill into place by crane
The boat ramp at Ocoee Dam No. 2
The boat ramp at Ocoee Dam No. 2
Drilling, Blasting, Hauling and Rock Bolting Progress
 
CHATTANOOGA, Tenn. – Work continues to progress on the U.S. 64 rockslide removal project.  Today and Wednesday, crews set off a series of blasts on the eastern slope and brought down a large amount of rock debris.  Today workers also blasted apart large boulders at the base of the mountain.  Crews also worked along the western side of the slide grouting rock bolts into place and continued installing rock bolts. 
 

Polk County US-64 Rockslide Update For February 24

Wednesday, February 24, 2010 | 04:21 pm
Debris Hauling, Drilling, Rock Bolting and Blasting Continue
 
CHATTANOOGA, Tenn. – This week construction crews with Blalock & Sons continued drilling the eastern slope in preparation for blasts scheduled for Thursday and Friday while heavy equipment worked below on the roadway surface and the river bank to break up rock debris, load it onto trucks and haul the material off site. Hayward Baker crews continued drilling and installing rock bolts on the western slope.
 
Crews will continue drilling the eastern slope, installing rock bolts on the western slope, and breaking up and hauling debris away from the site throughout the week.
 
Work will continue during daylight hours seven days a week. The contractor plans to implement nighttime work for various operations once they can be done safely.